Uzbekistan pours first concrete for world's first export SMR plant
Uzbekistan began construction of the first small modular reactor export order globally on June 4, with a $9.5B combined nuclear facility expected to supply up to 14% of the nation's power by 2033.
Ontario pours foundation for Western world's first commercial SMR
Ontario Power Generation installed a 2.1-million-pound basemat for the first GE Hitachi BWRX-300 reactor at Darlington, marking the transition from site prep to vertical construction on a CAD$20.9 billion, four-unit SMR project slated for 2030 grid connection.